Environmental Safeguarding
by Kimberly Paggioli, P.E.
July 1, 2011
 |
| Non-metallic pipe is set in place for the installation. |
|
Water and electricity do not mix. While it was important to ensure the stormwater was removed from the substation, it was also necessary to make certain no oil would escape the site and it all had to be automatic.
Headlines have been describing many types of industrial
accidents in months past. Many companies are taking measures to prevent the
negative environmental impacts such incidents cause. One such example is an
electric utility that serves more than three million customers across the
Southeast United States, which fixed an issue at two of their 500-kilovolt (kV)
substations.
Electrical distribution
 |
| Hobas fittings join easily in the field using the standard FWC coupling. |
|
When power leaves any generating plant, it travels to massive
substations that begin the distribution process. Electricity arrives at 500,000
volts and must be stepped down to a lower voltage for its secondary
distribution to successive substations in the power grid, where it eventually
splits off to various residential neighborhoods and commercial zones.
Such substations are constructed with drainage
systems that collect rainwater to be channeled away from the electrical
transformer and discharged into a nearby creek or tributary to a river. Because
these initial distribution transformers deal with massive amounts of voltage,
they are encased in several thousand gallons of oil for cooling.
Preventing oil spills
 |
| Hobas pipe can be easily modified in the field. Here a worker cuts a hole to provide a connection for a smaller pipe. |
|
In order to devise the most efficient containment system
possible to protect against a transformer leak, the utility provided research
funds to several engineering firms to design an interceptor and underground oil
containment system for the two existing 500-kV substations. These
computer-controlled substations are unmanned, and therefore the challenge of
designing the system lay in its automation capability to sense an oil spill on
its own. The electric utility also wanted a pipe material that would be
impervious to most of the chemicals with which it could come in contact,
particularly oil, and they wanted a joining system that would not leak into the
subsurface soils.
They chose a design submitted by civil engineers at
Davis-Martin-Powell & Associates (DMP) of High Point, N.C. Ben Palmer,
P.E., the DMP engineer in charge of the project, worked with Don Joyce of
Pomona Pipe Products, Greensboro, N.C., who suggested pipe materials for the
project. Both Joyce and Palmer had experience with the joint and chemical
resistance of Hobas pipe, and specified it based on that experience.
Palmer's plan to intercept the drainage system
involved installing an oil stop valve that would be sensitive to the specific
gravity of the liquid in the chamber. Water inside this chamber would cause the
valve to float, allowing the water to continue outward to public drainage. If oil
were sensed inside this chamber, the valve would not open because oil is less
dense and lacks the buoyancy to lift the valve.
 |
| Corrosion resistant fittings are custom-made per project requirements. |
|
"The bank of transformers is situated atop a rock field
sump," said Palmer. "The sump areas are connected to a storm drain
pipe that conveys the stormwater runoff off-site and drains these sumps during
a rainfall event."
The oil stop valve was installed inline on the storm
drainpipe, leaving the site. Inside of the oil stop valve structure, a precast
structure houses the oil stop valve along with a diversion pipe leading into
the containment system.
In the event that the valve sensed oil and remained closed,
the oil-contaminated water would be funneled into an underground containment
reservoir that was constructed of six-foot diameter pipe, where it would
temporarily remain until it could be manually pumped out and properly disposed.
"The design capacities for the two sites were based
upon containment of a single piece of equipment and the rainfall from a
25-year, 24-hour storm event," said Palmer. "The concept was very
similar to an underground stormwater detention facility, just a different
application."
The containment vessels are made up of
custom-made elbows and tees to create manifolds and 90- to 104-foot long
straight runs, according to Matt Swenson of Power Consulting LLC, the on-site
inspector for the utility. The straight sections used were 20 feet long and
weighed about 7,000 pounds.
 |
| One of the straight stretches of Hobas is installed using an excavator. Lightweight Hobas pipe does not require the heavy machinery needed for concrete pipe. As the contractor set each piece, they backfilled a portion to hold the pipe in place and avoid the need for manipulation when tying into the manifold at the end of the run. |
|
One substation's containment vessel covers a footprint of 26
feet by 104 feet and is composed of 328 lineal feet of 72-inch pipe in three
straight runs for a capacity of 60,750 gallons. The other 500-kV substation's
vessel covers a footprint of 36 feet by 90.25 feet with 383 lineal feet of
72-inch Hobas pipe in four straight runs for a capacity of 81,560 gallons.
According to Joyce, the pipe had been pre-ordered and was
onsite when the contractors arrived.
The installation was performed by different contractors at
the two different sites, neither of whom had prior experience with this pipe.
Quartermaster Environmental, Shelby, N.C., installed one system and Willis
Construction Co. installed the other.
Each 72-inch pipe containment reservoir was installed in a
12-foot deep excavation atop a one-foot base of washed stone and topped with
five to six feet of cover. There was a learning curve in handling and placing
the sections, with correct placement being critical in order to make the
straight runs and enable the manifolds to properly join at opposite ends,
approximately 100 feet apart, according to Swenson. "As the contractor set
each piece, they backfilled a portion to hold the pipe in place so that there
would be no need for manipulation when tying into the manifold at the end of
the run.
"I feel both projects were a success and I
understand that both are operating correctly now a year later, namely that they
are dry." PE
|