Solidification/stabilization treatment at a wood-preserving- turned Superfund site.
 |
| A pugmill was used for S/S treatment of materials prior to placement. |
|
Solidification/stabilization (S/S) treatment is being used
as a remedial component to treat contaminated soils and sediments at the
Brunswick Wood Preserving Superfund Site in Brunswick, Ga. This site was placed
on Superfund's National Priorities List in 1997 and currently is undergoing
remedial action under the designation Operable Unit One (OU1).
The site is an 84-acre former wood treating facility,
operated from 1958 until 1991. Three major types of wood preservatives
prevalent at the time were used at the site: creosote, which consists of many
polycyclic aromatic hydrocarbons (PAHs), pentachlorophenol (PCP, which is
associated with dioxin), and chromium/copper/arsenate (CCA).
Wood-treating activities were historically conducted at many
areas of the site, including process areas, storage areas, the rail spur that
ran along the southern end of the site, and several ponds or surface
impoundments (IMs). On its western end, the IM-1 pond was used during the 1960s
and later buried, while the IM-2 pond was where creosote processing was taking
place at the time operations ceased in 1991. On the site's eastern end, the
IM-4 and IM-5 spray ponds were used for spent creosote. Wood preservative
chemicals were released to surrounding soils and surface waters as a result of
these operations.
After a fire in early 1991, the EPA responded with a
four-year removal action that included many activities. All but a few of the
site structures were demolished and removed. Sludges were dewatered. Wastewater
was treated. Drums and lab wastes were disposed off site. Poles, lumber,
equipment and scrap metal was recycled or salvaged. And contaminated
soils/sediments were excavated and stockpiled onsite in four encapsulated waste
cells, each covered by a geomembrane. The EPA's removal costs were
approximately $12 million.
In 1997 and 1998, the state of Georgia conducted its own
removal action at the former wood treatment site, during which the three
largest cells, primarily containing soils/sediments impacted by creosote and
PCP, were disposed off site. The state's removal costs were approximately $18.5
million.
The selected remedy for OU1 utilized a containment strategy
to encapsulate contaminants remaining onsite. The chosen remedy components
included the construction of subsurface barrier walls around the old creosote
ponds, which were located on the eastern and western ends of the site. These
consisted of trenches that would need to be filled with a soil/bentonite mix
and keyed into the weathered limestone aquitard, located 50 to 65 feet below
grade.
The proposal called for engineered caps to be
placed over the areas contained within the barrier wall. Groundwater outside
each of the cap/wall footprints would be treated in-situ with chemical
oxidation to enhance natural degradation of contaminants. The caps would
include subcaps consisting of approximately 75,000 cu. yards of
solidified/stabilized (S/S) materials from the creosote impoundments, Burnett
Creek, site soils above the performance standard of 1 part per billion set for
dioxin, and the remaining waste cell onsite (which contain CCA-impacted soils).
The S/S remedy component could be applied to these subcap materials.
S/S treatment
 |
| S/S-treated material mixed to a consistency of damp soil. |
|
S/S treatment involves mixing a binding agent, commonly
portland cement, into contaminated soil, sediment, sludge or waste. Successful
treatment is accomplished through physical changes to the treated material and,
often, chemical changes to the hazardous constituents themselves.
S/S treatment operations may be conducted either ex- or
in-situ. During ex-situ treatment, the waste material is first excavated then
mixed with the S/S binding agent, commonly with excavators or in pugmills.
Ex-situ treatment can be performed entirely on site by a mobile treatment plant
transported to the site. During in-situ treatment, contaminated material is
mixed with S/S binding agents while the material remains in place , commonly
with excavators, horizontal rotary soil mixers or deep soil mixing augers.
S/S treatment technology contributes to greening
their remediation processes through sustainable development of a contaminated
property. While immobilizing hazardous constituents, the technology also can
improve the construction properties of the treated materials, enabling their
reuse.
Reuse of S/S-treated material in capping system
 |
| S/S-treated materials were placed, layered and then compacted with a bulldozer. The final cap was at least 3 feet thick and then covered with at least 2.5 feet of soil in order to support proper vegetation growth. |
|
The remedy includes the construction of caps over the former
creosote impoundments on the eastern and western ends of the site. The caps
will extend significantly beyond the pond footprints of these former
impoundments.
The footprints were established for an informal groundwater
standard of 1,000 ug/L of total semi-volatile organic compounds to capture
groundwater contamination within the barrier walls. The capping system
consisted of subcaps, geosynthetic clay liners, and a 2.5-foot thick vegetative
soil layer. S/S treated material was used as the construction material for the
subcaps. Freshly mixed S/S-treated material was discharged from the pugmill
into dump trucks and then transported to the former impoundment areas, where
the material was dumped and then spread and compacted by bulldozer. Successive
layers of the material were placed to form subcaps of at least 3 feet thick
over the pond footprints themselves. Future plans call for a geosynthetic clay
liner to be installed on top of the subcaps, and a 2.5-foot soil layer to be
placed on top of the geosynthetic clay liner as a vegetative soil cover.
The use of S/S treatment technology in the remedy will
contribute to the future redevelopment options of the property. The strength of
the capped areas resulting from the cement-treated subcaps will support the
replacement of a former rail spur across the western wall/cap, while the
eastern wall/cap will accommodate a potential concrete parking area.
Onsite management of the 75,000 cu. yards of
S/S-treated material avoided nearly 4,200 dump truck roundtrips to transport
the material to off-site disposal and replacement fill.
PE