Fighting corrosion to
preserve a historic racetrack, installers raced the calendar to upgrade
critical stormwater management systems before the first gun of the 2007
horseracing season.
Installation
 |
| The 21-foot trench width at Suffolk Downs allowed for only a 2-foot clear space between the Hobas pipes and a 1 1/2-foot clear space to the trench wall. |
|
“The pipe went together well, and was embedded with
flowable fill and backfilled with select compacted materials to grade,” said
Steve Pini, superintendent for the racetrack. “The surface work and track
restoration began after Revoli reached grade.”
Phase one included restoring the
hydraulic capacity of the drainage system at the two uppermost locations to
restore hydraulic capacity and remove blockages. Phase two included replacing
the downstream twin 60-inch diameter HDPE pipes with 96-inch CCFRPM pipes, as
well as channel and lagoon dredging.
“The 60-inch HDPE pipes were a temporary emergency repair
done a few years ago after the collapse of the existing 108-inch corrugated
line,” said Pini. “The corrosion from the soils and tidal location cut through
the corrugated pipe like a razor blade. We knew we would come back with a
permanent fix.”
CCFRPM was the only material
specified for the storm drainage improvement piping because of its resistance
to corrosion, hydraulic capacity and abrasion resistance. Detailed material
specification also included specifics on the interior surface of the pipe,
requiring a 50-percent elongation on the resin used. This was required to
achieve the necessary abrasion resistance. Proof of prior performance of the
pipe product was required. A five-year history and a list of 500,000 feet of
installed pipe were required with the submittal package. Since timing was
critical, the project specifications included a guaranteed pipe delivery
timeframe.
“Work
can be performed only in the off-season for the track between Dec. 1,
and March 1,” said Shawqi Alsarabi,
the contractor’s president. “March 1,
2006, was the completion date for phase one, and March 1, 2007, was the
completion date for phase two.” The tight schedule was caused by the fact
that work involved removing and replacing a building and two sections of the
track.
The pipe manufacturer worked with
the contractor and designer to provide installation recommendations for the
tricky twin barrel installation submerged in flowable fill by direct
bury. The 21-foot trench width allowed for only a 2-foot clear space between
pipes and a 1 1/2-foot clear space to the trench wall. The native soil material
at the 12-foot cover depth had a constrained modulus of only 700 psi (SPT N=2
blows per foot minimum).
To combat the poor properties of native materials and
minimize settlement, a flowable fill was specified for the embedment material.
To increase its strength, the fill was allowed to develop before the cover
material was placed. “We worked in a tight trench to minimize the amount of
soil removed and to save on flowable fill,” said Alsarabi. “The 72-psi pipe
stiffness ... performed well even in difficult conditions.”
Much of the work on the project
was performed in a stormwater drainage channel, and was subject to storm
conditions and fluctuations in water levels. The contractor was required to
provide a means to work in the presence of water in the channel, storm events
and tidal impacts.
Given the geography of the
area, installers constantly battled the storm surge. “We had [an obstacle
with] the tide gates during heavy rain and the high tide, which made
our bypass ineffective during those events, especially during the second
phase,” said Alsarabi. Even given the difficult conditions and quick timing, he
added, “The pipe performed well.”
PE