Understanding Performance-Based Contracts
by Mark Vigneri
April 1, 2010
An executive's guide to the benefits and pitfalls of a growing payment principle for remediation services.
Pay-for-performance (PfP) remediation of soil and/or groundwater
is not a very well-understood subject in general business, mostly because there
are so many variations of the subject. PfP should be regarded as a technical
strategy and contracting method to compensate a remediation company. It should
be based on matching payment with actual contaminant mass reduction with the
goal towards site closure.
The secret ingredient in an effective performance program is
the ability to match up the site owner's goals with the capability of the
remediation contractor. Typically, this means reaching agreed-upon goals within
a specified budget.
The first wide-scale, in-situ performance-based program
was developed in 1998 by ERFS, Sea Girt, N.J., for the Pennsylvania Underground
Storage Insurance Fund. It involved scores of sites contracted on a not-to-stop
basis, with predetermined volumes of soil and groundwater being remediated
until complete. Compensation was based on pre-defined milestones of contaminant
reduction along the path to achieving remedial goals. Since that time, the
remediation company's work has been approximately 80-percent based on
performance.
Implementing the approach
 |
| During any cleanup, it is important to take steps to prevent further site contamination. Photography supplied by Steven Parke.
|
|
PfP has two types of implementation. The first is the
desired even playing field, where all involved parties have well-defined risks
or exposure, and the remedial plan, with contingences, is functional, flexible
and well defined for real-world conditions. The other strategy is skewed more
toward assigning risk than the management of risk. If the plan favors the
contractor, then payments can exceed real performance. If the plan favors the
site owner too much, then the remediation company may be faced with having to
reach unrealistic performance levels just to cover project costs.
To avoid possible failure of a skewed plan, certain building
blocks are needed in the overall plan.
Foremost, PfP cannot be a guess or a singular event; it has
to be a program. Also, key attributes of the provider and the client increase
the chance for a mutually pleasing resolution to the contract. In our
experience, the most important attributes for the provider are experience,
in-house technology, and a sound financial model. Up to 60 percent of our
business is from environmental consultants or engineering firms, who in turn,
do business with 80 percent of our direct clients for services we do not
provide, such as civil engineering, or independent reporting. ERFS runs a
performance-based program that grew on the experiences of over 500 sites and a
100-percent contract completion rate. All technologies are in-house continually
developed and updated, with 18 contracting models that are managed by an
actuarial process.
Alternatives to actuarial modeling are 1) external
insurance-based models, and 2) risk-to-reward-based factoring. Comparatively,
insurance- and risk-to-reward-based models are fixed in nature. Insurance-based
models run on assumptions that an overdesigned approach with high capital cost
covers probable contingencies and unknown events, or that project failures
cause a punitive process to take over. Risk-to-reward models are based on
performance, remuneration and fallback reserves. If something goes wrong, there
are usually few options to recovery.
Actuarial-based is the most complex model, because the data
and calculations that build a fixed cost-design change over time. Factors for
this include current costs to provide services; retainage from prior closed
sites; cost-of-money rates (internal and external) related to collection of
performance milestone payments; and degradation profiles of technology verses
contaminants and geology in volumes of groundwater and soil. Even frequency of
like operations or proximity of projects effect costing in an actuarial
process, because costing is based on an ever-updating schedule of work in
progress managed as one actuarial matrix of true costs, past, present and
future.
An actuarial model is very flexible for technology changes
within a project, such as adding additional injection points, or changing
oxidant types in mid-project. This is all done without additional charge to a
client, because the financial model allows many types of field changes.
The problem faced by remediation companies not
based in performance-based work is that they can get pigeonholed into an
insurance- or risk-to-reward-based model because in their view, each PfP
project is a standalone event, and not part of a wide, continuous program where
risk is spread among portfolios. On the other hand, the complications of such a
program may often be too much for clients and remediation providers. The key to
pulling it off is to follow three contracting principles: 1) good design, 2)
strong trust and equanimity between partners, and 3) simplicity.
Technical design
 |
| Most businesses have to stay in operation during a remedial activity. Care to not interrupt business activities is very important. Photography supplied by Steven Parke.
|
|
Delineation of a site needs only to be bracketed, not
perfect. Most important is that site characterization defines the horizontal
and vertical extent of the contamination, and the approximate levels, along
with the geology and hydrogeology. Information beyond this is a luxury that can
drive design costs down, but assume a whole volume needs to be treated.
In our recent experience, bench tests and pilots studies are
holdovers from the '90s. Unless an unusual compound, rare mix of contaminants
or difficult geology is involved, a bench test tells little about real-life
site applications. Bench tests are useful to study stoichiometric ratios or
chemistry, or testing can determine if there is a natural microbial population
to stimulate. But there is no real-world translation to the field.
Also, pilot study results are generally not transferable in
our experience, regardless of outcome. Even areas on the same site could have
non-interchangeable characteristics. Live fieldwork strategies provide
real-time bench and pilot test data in the early stages of a project and are
essential to a complete PfP work plan. Technology substitutions must be
preplanned and cost relatively the same. Contingency planning in performance
contracts requires that backup plans do not exceed the basic costs of the
primary plan.
Trust and simplicity
 |
| Not all cleanup sites are situated in easy-to-access areas. It is important to use care and preserve existing landscaping as much as possible. Photography supplied by Steven Parke.
|
|
The first rule in any performance program is that all
stakeholders have to win. No part of the contracting plan can reward failure,
or upon success, greatly reward another stakeholder at the expense of the
others. Communications must be even and open among all parties.
Further emphasizing the need for trust between business
partners, the contract needs to be a living document. The technical plan needs
to be based on very sound what/if/then planning. Field changes to a project
need to be planned to at least four to five contingency levels, in order to
accommodate possible scenarios.
One way to keep all parties on the same page is to keep the
contract as simple as possible, using only the most concrete terms and
conditions. Things like bonus payments for early completion generally do not
work, because they cause a possibility of field decisions being compromised.
Milestones for payment should be black-and-white in structure, easy to
understand, and easy (and of reasonable cost) to verify. A good rule is that if
the payment schedule requires any subjects that need to be audited or
interpreted, it probably is not going to work.
Remediation contractors need to understand the paying
client: 1) is not usually cleaning a site by free will, 2) this is not their
core business, and 3) the money spent on environmental is viewed as a loss to
the bottom line. True PfP work requires an understanding of some very advanced
economics to provide a business solution to a problem. To understand the
financial benefit of such a program for a client, which sometimes is their only
benefit, it is important to understand and be able to explain some rather
complicated financial and accounting concepts.
The science is not limited to technology. It
also involves all of the design features of the financial products that
minimize client risk. For example, any financial contracting model should not
only set milestone, payment and work completion schedules, but also set
financial modeling precepts so that the client's business accounting needs for
financial statements, taxes, or other reports can be produced. Common
reoccurring accounting subjects include the obvious: return on investment, and
less obvious focus percentage, i.e. the percentage of actual remediation costs
within total costs. End-of-lifecycle is a percentage of project progress that
becomes the main inverse to the all-important contingent liability calculation,
especially for public companies. Financial modeling is an enormous and
specialized subject on its own. Without an in-depth financial model, there is
no true way to manage the variable uses of technologies within a PfP project. PE
Sidebar: Case Studies
What does a successful project look like? Examples of PfP in
action may provide some insight:
1. In one case, a Department of Defense site in California
was on an original PfP contract that was adapted to new field discoveries
without interruption. Field changes involved injection methods, oxidant changes
and hand off to biological MNA.
2. Thirty-one gas stations in New Jersey, privately owned
portfolio, were being treated concurrently on a five-year schedule. All
expenditures matched operations on a complex completion matrix.
3. In Maryland, an oil terminal with 100 years of free
product accumulation was remediated in 90 days of active treatment. Payment was
earned and deferred, to be paid on a schedule not matching the field services.
4. Another oil terminal, this one in Florida, was retired in
time to become a parking lot for the Super Bowl. Because of contract terms, a
discovered abandoned pipeline did not interfere with closure of the site.
5. The owner of three dry cleaners in major shopping centers
around Dallas faced a mid-game technology substitution in the field, at no
additional cost to the client. The sites were completed as planned and
on-schedule.
6. A VOC site within an Illinois shopping center
was completed early. Invoicing stayed on the original timing schedule as
planned for the possible circumstance.
|