On the National Mall in D.C., workers were ready to break ground on a government building meant to bring peace and prosperity to the 21st century. But first, they had to make sure the 19th century sewers below could handle the pressure.
Structural requirements
 |
| As a 20-foot section of Hobas pipe is lowered into the excavation, the Lincoln Memorial can be seen in the background. |
|
The District of Columbia's
water and sewer authority, DCWASA, was given the task of ensuring reliability
of the area's infrastructure, including a brick sewer, reportedly built in
1896, that had been serving the area. Although it was in fair condition, with
only a few repairs required in recent years along its entire length, planners
decided that it needed permanent preservation to support future construction.
The planners also decided that
slipline rehabilitation was necessary to ensure the sewer would not interfere
with the future USIP facility. A centrifugally cast, fiberglass reinforced,
polymer mortar (CCFRPM) pipe met all of the project requirements listed by the
authority.
The approximate ground profile was 40 feet above the
top of the existing sewer. Depending on which of the final designs for the USIP
building was adopted, the proposed lowest level of the slab could have been as
near as 5 feet above the existing sewer. Regardless of the final design, the
pipe to be installed had to be structurally sound, grouted in place and capable
of handling the final loads.
Preserving capacity
 |
| The USIP has provided this architect's rendering of its permanent headquarters building project. (Photo courtesy of United States Institute of Peace, Washington, D.C.) |
|
The existing brick sewer was
sliplined with 360 linear feet of 69-inch diameter CCFRPM pipe from Hobas Pipe
USA, based in Houston. The actual inside diameter of the original brick sewer
varied from location to location, but was generally 73 to 75 inches. The
engineering firm thoroughly evaluated the host pipe conditions in order to
maximize the diameter of the sliplining pipe. The radial clearance calculated
between the pipe OD and the brick host pipe ID ranged between 0.25 and 1.25
inches.
The capacity of the existing
sewer in the area that was relined ranged from 103 to 119 MGD, while the
capacity after rehabilitation was calculated to be 101 MGD. Flow monitoring
after rehabilitation on previously installed projects showed a Manning's
roughness coefficient value of 0.009 to about 0.011.
Contracting CEO K. Michael Hall said, "It
appeared from our post TV run that the flow depths had indeed been lowered by
some 10 to 20 percent."
Slipped in easy
 |
| The brick construction of existing 19th century sewer was visible during the sliplining rehabilitation project for the proposed USIP building in Washington, D.C. |
|
"The sliplining went very well," said
Hall, "and after the pipe insertion, we grouted the annular space
ourselves with a lightweight grout and this also went very well. The inspection
ports revealed that the grouting filled the annulus completely. Three ports
were installed at the 12 o'clock position, spaced evenly along the 330-foot
run. Upon inspection, the ports were solid with grout. We removed the valves
and replaced the tapped holes with 1½-inch PVC plugs."
PE